TCWG Review of Qualitative Analyses

Qualitative PM Hot Spot Analysis Review
October 2007 Determination

LAE0465 I-5 HOV and Truck Lane Improvement

No conformity determination can be made at this time - There is no funding committment at this time. LAE0465 is included in the 2006 RTIP (Amendment No. 9) with funding to conduct a study only, not ROW or construction.

RIV060120 Van Buren and I-215

Not a POAQC - Hot Spot Analysis not required

LA000357 and LA000358 I-5 HOV from SR-134 to SR-118

No conformity determination can be made at this time - 1) Awaiting for EPA to approve EMFAC 2007. Per discussion, EPA has indicated that a decision may tentatively be made in early December; and 2) the TCWG has requested that the current Qualitative PM Hot Spot Analysis be revised to further explain traffic assumptions and distributions.